APRIL 2026 / UGANDA / 4th WATERTANK

The construction of the fourth water tank is moving really fast.

APRIL 2026 / NORTHERN UGANDA / DEEP WATER WELL

Great news: the deep-water well is ready to use! The community is incredibly happy and grateful for this new water source.

MARCH 2026 / UGANDA / 4th WATERTANK

Construction on the 4th water tank just kicked off!

MARCH 2026 / NORTHERN UGANDA / DEEP WATER WELL

After a bit of a delay, they’re finishing up the last bits of work. Once everything’s installed properly and the cement has dried, the pump can start being used. The community is looking forward to it

FEBRUARY 2026 / NORTHERN UGANDA / DRILLING A DEEP WATER WELL

Great news!! The drilling was successful. What a huge relief for the project manager, the community, and all of us. Big compliments to the project manager for her determination!

FEBRUARY 2026 / NORTHERN UGANDA / DRILLING A DEEP WATER WELL

Unfortunately, drilling the deep water pump in January didn’t work out. The amount of water that came up was too little, and the rock layer was too thick to drill through. Our project manager on site then picked a different location. After some delays—because the truck with the compressor wasn’t available—the new drilling work got started. So far, things are going well, and hopefully we’ll hit the water layer tomorrow. In the photo, you can see the soil and rock layers from 19 sections of the drilling.

JANUARY 2026 / UGANDA / COMMUNITY SPACE, LIBRARY, WATER TANKS

In partnership with our project manager, a German sponsor, the local community, and the Jawiba Foundation, we’ve launched a major new project: a community space with a library and water tanks. The combination of different funding sources and volunteers from the community is what’s making this possible. We’re hoping to have everything completed by the end of March.

DECEMBER 2025 / NORTHERN UGANDA / DRILLING A DEEP WATER WELL

On December 26, they started drilling a deep water well in northern Uganda (Pader District). They’ll continue tomorrow to break through the rock layer.

DECEMBER 2025 / UGANDA / DRILLING FOR DEEP WATER WELL

On December 23, we drilled for the deep water well. Unfortunately, it wasn’t successful. All the locations identified by the geology team turned out negative. At the first site, they drilled down to 100 meters, but no water was found. At another site, a 35-meter borehole looked promising at first, but the water output was very low. They waited overnight, and by morning they were expecting about 5,000 liters of water, but it turned out to be only about 5 liters. They continued drilling to 105 meters, but still found nothing. In January, the contractor plans to bring in a senior geological engineer from Kenya, since they were just as disappointed as we were. For now, he advised us to stick with rainwater collection or dig valley dams and install water pipes, a pump, and a tank so we can push water to the center of town.